Wastewater Treatment Project

thumbnail_site 1 7-17-24

Project description: Vosburg Road Pump Station, Wastewater Treatment Plant - Phase II, and Phillips Road to Tebor Road Conveyance Pipe upgrades.

Bonding information:

Bond Resolution amount ($):

Vosburg Road Pump Station                                     5,700,000

Wastewater Treatment Plant - Phase II                81,500,000

Coca-Cola/fairlife Conveyance Pipe                        7,100,000

___________________________________________________________

                                                                                   $94,300,000

Bond Resolution date: 7/27/2023 | Meeting Results | Meeting Video

Financing as a percentage of approved bond resolution: 78.8%

Life-to-date net project cost: $49,497,108

Life-to-date net project cost as a percentage of approved bond resolution: 52.5%

Project percentage complete: 74.5%