Project description: Phase I - North, South, and West Park, Phase II - East End of Park, and Phase III - Education Center and Signage.
Project timeline:
Bonding information:
Bond Resolution amount ($):
Phase I - North, South, & West Park 4,200,000
Phase II - East End of Park 1,140,000
Phase III - Education Center & Signage 160,000
_________________________________________________________
$5,500,000
Financing as a percentage of approved bond resolution: 31.3%
Life-to-date net project cost: $1,174,595
Life-to-date net project cost as a percentage of approved bond resolution: 21.4%
Project percentage complete: 73.3%